Street Projects

2022

Beech St., north of Lincoln Ave.
Birch St., north of E. Washington Ave.
Cherry Hill Dr.
Citrus Ln.
E. Jefferson Ave., between Birch St. and Lakeshore Dr.

TIMELINE:  The construction window allowed by contract is April 1 through October 21.  Work will begin with water main, storm sewer, and street excavation.  Curb and gutter, asphalt, and landscaping will be completed later in the summer.

Construction Timeline 05/12/22 – This schedule is a work plan subject to changes in the order of work or days to completion based on weather and subcontractor availability.

UPDATE 05/21/22:  The Village received a cost estimate from We Energies to bury overhead electric lines on E. Jefferson Ave.  The Public Works and Utilities Committee will consider amending the project scope to include this work.  They will also discuss replacing wooden street light poles with an alternative material.

UPDATE 05/12/22:  Preliminary work began today with removal of trees on E. Jefferson Ave.  The contractor and Village walked the project area to identify areas of concern, including trees in the rights-of-way that physically block construction or the operation of equipment, and trees whose root systems will suffer significant damage and are likely to die.  These trees will be removed prior to the start of construction.  Additional trees may be removed during the project where the trees present a hazard or the roots become irreparably damaged.

Clearing and grubbing is scheduled in the following order:
E. Jefferson Ave.
Citrus Ln.
Cherry Hill Dr.
Birch St.
Beech St.

Afterward, E. Jefferson Ave. will be the focus for construction, starting with water main and storm sewer installation.

PROPERTY OWNER INFORMATION:  Informational Flyer

2022 Street Projects – Engineered Drawings
2022-R-01  2022 Street Reconstruction Projects – PRELIMINARY RESOLUTION DECLARING INTENT TO LEVY SPECIAL ASSESSMENTS UNDER MUNICIPAL POLICE POWER PURSUANT TO SEC. 66.0703, WIS. STATS.
Preliminary Special Assessment Report – 2022 Street and Utility Projects


PASER is a rating system that classifies the condition of each street section in the Village using a State-defined system.  The Village Board hired Donohue & Associates in 2015 to prepare a report using the PASER classification system.  That report is provided below.  The ratings from the report were entered in the statewide PASER database and are updated biannually; the updated numbers are used to prioritize streets for maintenance, repair, rehabilitation, or reconstruction.  Streets that require rehabilitation or reconstruction are added to the Capital Improvement Plan.

2015 PASER Rating Report
Special Assessment Policy

2020

Park Ct.
W. Jefferson Ave.

Preliminary Special Assessment Report – 2020 Street and Utility Projects
Final Special Assessments DRAFT
Notice of Special Assessment Public Hearing 04-12-2022
2022-R-03 W. Jefferson Ave. and Park Ct. Street Projects – FINAL RESOLUTION AUTHORIZING PUBLIC IMPROVEMENTS AND LEVYING SPECIAL ASSESSMENTS AGAINST BENEFITED PROPERTY IN CLEVELAND, WISCONSIN

2023

Linden St., W. Washington Ave. south to Wildwood Ln
Maple St., W. Washington Ave. south to Park Ln.
W. Washington Ave., west of Westview St.

Last update 05/21/22 4:27pm